The Expected Schedule of Works is as follows.

Monard 22nd of November

Place ducting across road way between Twomeys Garage and National School

Duration 1 day

Stop/Go Traffic Management will be in place.

 

Bansha 23rd of November to 2nd of December

Dig and Replace failed Sections of Pavement on Main Carriage Way Between O’Heneys and the Railway Bridge

and at entrance to Galtee View Housing Estate

Duration 8 days

Stop/Go Traffic Management will be in place.

 

Monard and Bansha 5th of December to 16th of December

Monard: Renew Roadway on Main Carriageway between the Speedlimits

Bansha: Renew Roadway on Main Carriageway between O’Heneys and the Railway Bridge

Duration 10 days

Stop/ Go Traffic Management will be in place.